第一章第二章第三章
录
4 4 8 8 8 9 9 9 10 10 11 11 12 12 12 12 13 13 14 14 15 17 19 21
编制依据·····························工程概况·····························施工准备·····························
3.1 技术准备······························3.2 材料和构件准备···························3.3 施工人员准备····························第四章
施工工艺和技术措施························
4.1 施工流程······························4.2 埋件埋设·····························4.3 栏杆立柱、水平钢管安装
······················
4.4 扶手找位与划线··························4.5 扶手弯头配制····························4.6 扶手连接预装···························4.7 扶手固定·····························4.8 整修·······························4.9 表面刷漆·····························第五章
质量保证····························
5.1 质量标准·····························5.2 应注意的质量问题第六章
·························
成品保护····························
附件1:图集06J403-1第24页······················附件2:图集06J403-1第75页······················附件3:图集06J403-1第77页······················附件4:图集06J403-1第78页······················
2
附件5:图集06J403-1第161页·····················23
3
第一章编制依据
1、***省建筑设计研究院有限责任公司提供的设计图纸、设计变更及相关洽商;2、《建筑工程施工质量验收统一标准》(3、《人民防空工程施工及验收规范》(
GB 50300-2001);GB50134-2004)
GB50194-93)JGJ46-2005)GB 50210-2001)
2002年版;
4、《建设工程施工现场供用电安全规范》(5、《施工现场临时用电安全技术规范》(6、《建筑装饰装修工程质量验收规范》(
7、《工程建设标准强制性条文-房屋建筑部分》
第二章
1.建设单位:******有限公司
2.设计单位:***省建筑设计研究院有限责任公司
工程概况
3.工程名称:***1-2#、6-8#楼阳台栏杆、窗内护栏、楼梯扶手工程4.建设地点:***市5.工程概况:5.1、1#楼:
单栋建筑面积:10830㎡;建筑占地面积:2393.20㎡;建筑总高度:85.90m。建筑层数:地上29层,地下1层。户数:116户。建筑物耐火等级:一级。结构体系:剪力墙结构。建筑物设计使用年限:50年。建筑物抗震设防烈度:7度。1)1000mm高栏杆:
使用部位:阳台、空中花园、天井及外廊栏杆;规格:遍,饰面粉墨喷涂2)600mm高护栏:
1.1m高;面层:防锈底漆两
4
使用部位:屋顶天井护栏3)窗内组装式护栏:
规格:0.6m高,面层:防锈底漆两遍,饰面粉墨喷涂
使用部位:窗内护栏,规格:4)楼梯靠墙扶手:
0.9m高,面层:防锈底漆两遍,饰面粉墨喷涂
使用部位:楼梯内,做法:详图集06J403-1,75/K1 ,具体要求详建筑图纸
5)工程内容:后置埋件制作安装;栏杆制作:截料、焊接、焊缝打磨刷防锈漆两遍;栏
杆现场安装,并粉墨喷涂;栏杆安装完成后保护,并对原土建墙体破坏位置进行恢复5.2、2#楼:
单栋建筑面积:15151.43㎡;建筑占地面积:915.53㎡;建筑总高度:86.2m。建筑层数:地上28层,地下1层。户数:156户。建筑物耐火等级:一级。结构体系:剪力墙结构。建筑物设计使用年限:50年。建筑物抗震设防烈度:7度。1)1000mm高栏杆:
使用部位:阳台、空中花园、天井及外廊栏杆;规格:遍,饰面粉墨喷涂2)600mm高护栏:
使用部位:室外下自行车库坡道护栏、天井护栏;规格:两遍,饰面粉墨喷涂3)窗内组装式护栏:
使用部位:窗内护栏,规格:4)楼梯靠墙扶手:
使用部位:楼梯内,做法:详图集
06J403-1,75/K1 ,具体要求详建筑图纸0.9m高,面层:防锈底漆两遍,饰面粉墨喷涂
0.6m高;面层:防锈底漆1.1m高;面层:防锈底漆两
5)工程内容:后置埋件制作安装;栏杆制作:截料、焊接、焊缝打磨刷防锈漆两遍;栏
杆现场安装,并粉墨喷涂;栏杆安装完成后保护,并对原土建墙体破坏位置进行恢复5.3、6#楼:
5
单栋建筑面积:12375.2㎡;建筑占地面积:376.7㎡;建筑总高度: 97.650m。建筑层数:地上33层,地下1层。户数:132户。建筑物耐火等级:一级。结构体系:剪力墙结构。建筑物设计使用年限:1)1000mm高栏杆:
使用部位:阳台、空中花园、天井及外廊栏杆;规格:遍,饰面粉墨喷涂2)600mm高护栏:
使用部位:屋顶天井护栏、2层北侧外廊栏杆,规格:0.6m高;面层:防锈底漆两遍,饰面粉墨喷涂3)750mm高护栏:
使用部位:3层北阳台、2-3、19-21轴南阳台栏杆;规格:0.75m高;面层:防锈底漆两遍,饰面粉墨喷涂窗内组装式护栏:4)窗内组装式护栏:
使用部位:窗内护栏,规格:5)楼梯靠墙扶手:
使用部位:楼梯内,做法:详图集
06J403-1,75/K1 ,具体要求详建筑图纸0.9m高,面层:防锈底漆两遍,饰面粉墨喷涂
1.1m高;面层:防锈底漆两
50年。建筑物抗震设防烈度:7度。
6)工程内容:后置埋件制作安装;栏杆制作:截料、焊接、焊缝打磨刷防锈漆两遍;栏
杆现场安装,并粉墨喷涂;栏杆安装完成后保护,并对原土建墙体破坏位置进行恢复5.4、7#楼:
单栋建筑面积:11243.3㎡;建筑占地面积:339.09㎡;建筑总高度:97.650m。建筑层数:地上33层,地下1层。户数:132户。建筑物耐火等级:一级。结构体系:剪力墙结构。建筑物设计使用年限:50年。建筑物抗震设防烈度:7度。1)1000mm高栏杆:
使用部位:阳台、空中花园、天井及外廊栏杆;规格:遍,饰面粉墨喷涂2)600mm高护栏:
1.1m高;面层:防锈底漆两
6
使用部位:屋顶天井护栏、2层北侧外廊栏杆;规格:0.6m高;面层:防锈底漆两遍,饰面粉墨喷涂3)750mm高护栏:
使用部位:3层北阳台、2-3、19-21轴南阳台栏杆;规格:0.75m高;面层:防锈底漆两遍,饰面粉墨喷涂4)窗内组装式护栏:
使用部位:窗内护栏,规格:5)楼梯靠墙扶手:
使用部位:楼梯内,做法:详图集
06J403-1,75/K1 ,具体要求详建筑图纸0.9m高,面层:防锈底漆两遍,饰面粉墨喷涂
6)工程内容:后置埋件制作安装;栏杆制作:截料、焊接、焊缝打磨刷防锈漆两遍;栏
杆现场安装,并粉墨喷涂;栏杆安装完成后保护,并对原土建墙体破坏位置进行恢复5.5、8#楼:
单栋建筑面积:12959.36㎡;建筑占地面积:5.31㎡;建筑总高度:97.75m。建筑层数:地上33层,地下1层。户数:132户。建筑物耐火等级:一级。结构体系:剪力墙结构。建筑物设计使用年限:1)1000mm高栏杆:
使用部位:阳台、空中花园、天井及外廊栏杆;规格:遍,饰面粉墨喷涂2)600mm高护栏:
使用部位:屋顶天井护栏、2层北侧外廊栏杆;规格:0.6m高;面层:防锈底漆两遍,饰面粉墨喷涂3)500mm高护栏:
使用部位:室外下自行车库坡道护栏;规格:粉墨喷涂4)窗内组装式护栏:
使用部位:窗内护栏,规格:5)楼梯靠墙扶手:
0.9m高,面层:防锈底漆两遍,饰面粉墨喷涂
0.5m高;面层:防锈底漆两遍,饰面
1.1m高;面层:防锈底漆两
50年。建筑物抗震设防烈度:7度。
7
使用部位:楼梯内,做法:详图集6.工程内容:
06J403-1,75/K1 ,具体要求详建筑图纸
后置埋件制作安装;栏杆制作:截料、焊接、焊缝打磨刷防锈漆两遍;栏杆现场安装,并粉墨喷涂;栏杆安装完成后保护,并对原土建墙体破坏位置进行恢复7.工程材料:
图纸设计要求:60×60×3钢管、60×40×3钢管、50×50×4钢管、50×25×3钢管、50×40×3钢管、40×40×2钢管、30×30×2钢管、20×20钢管、预埋件详图集06J403-1,161/M5等
工作联系单调整内容:
20×20钢管调整为20×20×1.2钢管;60×60×3钢管调整为60×40×2.5钢管;50×25×3钢管调整为50×25×2.5钢管;50×50×4钢管调整为50×50×2.5钢管
第三章
3.1 技术准备
施工准备
施工前应熟悉图纸、设计变更、图集相关要求,了解相关安全、质量规范,了解掌握栏杆、扶手的施工工艺,找出施工中安全质量施工注意点,做到施工中重点突出、心中有数。编制施工方案用以指导施工,逐级进行技术交底。3.2 材料和构件准备3.2.1 材料准备
1、木制扶手一般用硬杂木加工成规格成品,其树种、规格、尺寸、形状按设计要求。木材质量均应纹理顺直、颜色一致,不得有腐朽、节疤、裂缝、扭曲等缺陷;含水率不
8
得大于12%。弯头料一般采用扶手料,以求备弯头料。
45°角断面相接,断面特殊的木扶手按设计要
2、其他材料:木螺丝、砂纸、加工配件、油漆。3.2.2 机具准备
1、电动机具:手提电钻、小台锯。
2、手动工具:木锯、窄条锯;二刨、小刨、小铁刨;斧子、羊角锤、扁铲、钢挫、木挫、螺丝刀;方尺、割角尺、卡子等。3.2.3 作业条件
1、楼梯间墙面、顶棚等抹灰全部完成。2、金属栏杆或靠墙扶手的固定埋件安装完毕。3.3 施工人员准备
1、施工人员必须熟悉相关规范、图集的要求及栏杆、扶手安装工艺要求。施工前进行详细技术交底和专业培训,选取一层楼梯间进行样板施工,确认工序及做法后进行大面积施工。
2、坚持特殊工种持证上岗制度,并于施工前进行教育培训。
3、实行三级交底制度,即:技术部对项目部相关管理人员和分包技术人员进行方案交底;工程部对分包工长、班组长进行交底;分包工长、班组长对楼梯栏杆扶手施工工人进行技术交底。
第四章
4.1 施工流程
(1)不靠墙栏杆扶手
施工工艺和技术措施
9
埋件埋设→栏杆立柱安装→扶手找位与划线→扶手弯头配制→扶手连接预装→扶手固定→扶手整修→栏杆立柱、扶手表面刷漆。
(2)靠墙栏杆扶手
埋件埋设→水平钢管安装→扶手找位与划线→扶手弯头配制→扶手连接预装→扶手固定→扶手整修→栏杆立柱、扶手表面刷漆。4.2 埋件埋设
(1)不靠墙楼梯栏杆下部连接须在每个踏步上埋设埋件,由于现场楼梯已施工完成,并未埋设埋件。故须在每个踏步上按照图集图见下图。其中膨胀螺栓采用
06J403-1类型要求进行埋件定位,预埋件详
4A6,锚入混凝土深度35mm。
1200mm进行定位,由于结构、砌筑墙
(2)靠墙扶手埋件间距按照设计要求不大于
已经施工完成,并未埋设埋件。当预埋件位置在混凝土结构上时,采用膨胀螺栓锚入结构中,预埋件具体要求如(
1)所述;当预埋件位置在砌筑墙上时,须从砌筑墙掏出砌块,
C25混凝土进行浇筑,并振捣密实。
安装好埋件,埋件按设计指定图集选用,再用
3、锚板采用6mm厚钢板,如上图进行开孔加工。4.3 栏杆立柱、水平钢管安装
1、栏杆立柱安装
(1)栏杆立柱选用按图纸及图集选用;
(2)埋件埋设完成后,在各个埋件上对栏杆立柱进行划线定位,立柱中心距楼梯边缘不小于50mm;
(3)立柱高度按照工程设计、图集要求先加工好,立柱与锚板焊接时须保证立柱的垂直度;
10
(4)立柱中心间距为G/2,起步立柱中心距栏杆扶手起步边缘为中心距墙为G/2,G为踏步宽度;
120mm,终点立柱
(5)待踏步装修层完成,须在立柱与踏步接触部位安装法兰盘,并用粘结剂粘结牢固。
2、靠墙扶手水平钢管安装
(1)靠墙扶手水平钢管采用应符合图纸及图集要求;
(2)埋件埋设完成后,在各个埋件上对扶手水平钢管进行划线定位,同一梯段的水平钢管连线坡度与楼梯坡度相同;
(3)水平钢管伸出长度须满足扶手安装要求。
(4)在墙面装修层完成后,须在钢管与墙面接触部位安装法兰盘,并用粘结剂粘结牢固。
4.4 扶手找位与划线
1、安装扶手的固定件:位置、标高、坡度找位校正后,弹出扶手纵向中心线。2、设计扶手构造,根据折弯位置、角度,划出折弯或割角线。
3、在楼梯栏杆顶面,划出扶手直线段与弯头、折弯段的起点和终点的位置。4.5 扶手弯头配制
1、按栏杆顶面的斜度,配好起步弯头,一般木扶手,可用扶手料割配弯头,采用割角对缝粘接,在断块割配区段内最少要考虑三个螺钉与支承固定件连接固定。大于断面的扶手接头配制时,除粘结外,还应在下面作暗榫或用铁件铆固。
70mm
11
2、整体弯头制作:先做足尺大样的样板,并与现场划线核对后,在弯头料上按样板划线,制成雏型毛料(毛料尺寸一般大于设计尺寸约
10mm)。按划线位置预装,与纵向
直线扶手端头粘结,制作的弯头下面刻槽,与栏杆扁钢或固定件紧贴结合。4.6 扶手连接预装
预制木扶手须经预装,预装木扶手由下往上进行,先预装起步弯头及连接第一跑扶手的折弯弯头,再配上下折弯之间的直线扶手料,进行分段预装粘结,粘结时操作环境温度不得低于5℃。4.7 扶手固定
分段预装检查无误,进行扶手与栏杆上固定件,用木螺丝拧紧固定,固定间距控制在400mm以内,操作时应在固定点处,先将扶手料钻孔,再将木螺丝拧入,不得用锤子直接打入,螺帽达到平正。4.8 整修
扶手折弯处如有不平顺,应用细木锉锉平,找顺磨光,使其折角线清晰,坡角合适,弯曲自然、断面一致,最后用木砂纸打光。4.9 表面刷漆
对栏杆硬木扶手表面做底油一道,清漆两道;栏杆立柱金属部分均采用红丹防锈漆打底,喷蓝灰色油漆两道。
表面刷漆之前,必须保证木扶手表面光滑,刷漆须保证各处均匀,不漏刷;立柱和水平钢管表面经磨平,抛光后及时刷防锈漆,避免受潮起锈斑,后上面漆。
12
第五章
5.1 质量标准5.1.1 一般要求
质量保证
(1)有构件下料应保证准确,构件长度允许偏差为1mm。
(2)构件制作时保证项目:规格尺寸正确,表面光滑,线条顺直,曲线面弧顺,楞角方正,无戗槎、刨痕、锤印等缺陷。
(3)构件安装时保证项目:位置正确,割角线准确、整齐,接缝严密、坡度一致,粘结牢固、通顺,螺帽平正,出墙尺寸一致。
(4)硬木扶手选型、材质形状、尺寸应符合设计要求。
(5)安装固定扶手的预埋件必须牢固,无松动现象,木扶手入墙处应做防腐处理。(6)构件焊接时构件必须放置的位置准确,焊接时构件之间的焊点应牢固,焊缝应饱满,焊缝表面的焊波应均匀,不得有咬边、未焊满、裂纹、渣滓、焊瘤、烧穿、电弧擦伤、弧坑和针状气孔等缺陷焊接完成后,应将焊渣敲净,构件焊接组装完成后,应适当用手持机具磨平和抛光,使外观平顺光洁。5.1.2 强制性要求
(1)楼梯段(坡段)栏杆高度不小于(2)转角处栏杆高度不小于
0.9m。
0.10m高度内不应留空,且栏杆高
0.9m。
(3)最高楼层的楼梯水平段临空处栏杆离地面度为不小于1.2m。
注:上述栏杆高度指地面完成面至扶手最高点的距离。
13
5.2 应注意的质量问题
1、尺寸超出允许偏差:对焊缝长宽、宽度、厚度不足,中心线偏移,弯折等偏差,应严格控制焊接部位的相对位置尺寸,合格后方准焊接,焊接时精心操作。允许偏差项目见表一。
表一:楼梯扶手安装允许偏差
项
目
允许偏差 (mm)
3 3 4 3
检查方法吊线尺量检查尺量检查拉通线尺量检查
尺量检查
栏杆(板)垂直
栏杆间距扶手直线度扶手高度
2、焊缝裂纹:为防止裂纹产生,应选择适合的焊接工艺参数和焊接程序,避免用大电流,不要突然熄火,焊缝接头应搭接
10~15mm,焊接中不允许搬动、敲击焊件。
3、表面气孔:焊接部位必须刷洗干净,焊接过程中选择适当的焊接电流,降低焊接速度,使熔池中的气体完全逸出。
第六章
成品保护
1、安装扶手时,应保护楼梯栏杆、楼梯踏步和操作范围内己施工完成的项目。2、木扶手安装完毕后,宜刷一道底漆,并应加包裹,以免撞击损坏和受潮变色。3、扶手安装后应及时包裹保护。
14
附件1:图集06J403-1第24页
15
16
附件2:图集06J403-1第75页
17
18
附件3:图集06J403-1第77页
19
20
附件4:图集06J403-1第78页
21
22
附件5:图集06J403-1第161页
23
24